ALAwaabsLawGuide.co.uk
Timescales · SI 2025/1042

Awaab's Law Timescales Explained: The 24-Hour, 10-Day and 12-Week Rules

The three statutory deadlines at the heart of Awaab's Law — and exactly what each one requires.

Awaab's Law (SI 2025/1042) creates four distinct statutory timeframes for registered social housing providers in England. Missing any of them carries significant enforcement risk. This guide explains each deadline in plain English — when the clock starts, what it requires, and what happens if it is missed.

Day 0: The date of awareness

Every Awaab's Law clock starts from Day 0 — the date the landlord becomes aware of a hazard. This is not the date of the formal complaint, the date the inspection is booked, or the date the works contractor arrives. It is the date the landlord first has knowledge that a damp, mould, or hazard issue may exist.

Day 0 awareness can be triggered by a phone call to the repairs team, a written complaint, an email from the tenant, a note on an inspection report, or a contractor flagging an issue during another visit. The definition is deliberately broad. Landlords who attempt to argue that awareness only began when a formal repair request was logged — rather than when the issue was first mentioned — will face scrutiny from the Ombudsman.

Practical implication: every frontline team member who might receive a tenant report — repairs desk, estate manager, housing officer, contact centre — needs to understand that Day 0 begins when they receive that information, and it must be recorded immediately.

The 24-hour emergency deadline

Where a hazard poses an imminent risk to the health or safety of a resident, the landlord must begin emergency remediation works within 24 hours of Day 0. This is a clock that starts on Day 0 itself — not Day 1 — and it runs through weekends and bank holidays.

The threshold for the emergency clock is "imminent risk" — not every hazard, and not every instance of damp or mould. The emergency standard applies to hazards where the risk to life or serious harm is immediate: a broken boiler in winter with a vulnerable household, severe mould in a room used by an infant, structural instability, gas or electrical faults.

"Begin" in the context of the emergency deadline means commencing the works themselves — not booking an appointment, not sending an acknowledgement letter, not commissioning a survey. The landlord must have operatives on site or a remediation response actively underway within 24 hours.

For out-of-hours emergencies, this requires an active out-of-hours service. The 24-hour clock does not pause for weekends or evenings.

The 10 working day deadline — investigation and action plan

For hazards that do not meet the emergency threshold, the landlord has 10 working days from Day 0 to complete a full investigation and provide the tenant with a written Remediation Action Plan.

Working days exclude weekends and UK bank holidays. Day 1 is the first working day after Day 0. So if a report is received on a Friday, Day 1 is the following Monday.

The investigation must be substantive — a genuine assessment of the cause and extent of the hazard, not a superficial walk-through. It should be documented, ideally with moisture meter readings, photographs, and identification of the probable root cause (condensation, penetrating damp, rising damp, structural defect, ventilation failure).

The written Remediation Action Plan must then be provided to the tenant. This document must set out: what works will be done, in what order, by whom, and with what expected completion date. It is a statutory communication — a verbal assurance or an informal message is not sufficient.

Under Regulation 9 of SI 2025/1042, a written summary of the investigation must also be provided to the tenant within 3 working days of the investigation being completed. This is a separate obligation from the 10-day action plan deadline.

The 12-week completion deadline

All remediation works must be completed within 12 weeks of the written summary being provided to the tenant. Twelve weeks is 84 calendar days — again, this is not working weeks but calendar weeks, running through weekends.

The completion deadline applies to all preventative and remediation works identified in the action plan. Minor works that could reasonably have been done sooner should not be deferred to the end of the 12-week window.

Extensions are permitted where the full scope of works cannot reasonably be completed within 12 weeks — for example, major structural work requiring planning permission, or specialist treatment requiring dry conditions. But extensions must be agreed in writing with the tenant and documented. They cannot be assumed or imposed unilaterally.

The 5 working day safety works trigger

There is a fourth deadline that is sometimes overlooked: safety works must begin within 5 working days of the investigation being completed, even if full remediation will take longer. Where the investigation identifies a hazard that poses a risk — even if not an immediate emergency — the landlord cannot simply wait for the full action plan to be delivered before commencing any works.

What happens if you miss a deadline

The Housing Ombudsman investigates complaints where deadlines have been missed and can make findings of service failure, maladministration, or severe maladministration. These findings are published, named, and scrutinised by the Regulator of Social Housing.

Compensation orders are common. In 2024–25, the Ombudsman ordered compensation in over 40% of damp and mould cases. Cases involving missed Awaab's Law deadlines typically attract higher awards than equivalent pre-2025 cases because the statutory framework provides clear, measurable benchmarks against which failure can be assessed.

The RSH uses Ombudsman data as part of its Consumer Standards assessments. A pattern of deadline failures can trigger formal engagement, a regulatory notice, or in severe cases an in-depth assessment.

Using the deadline calculator

Our free Awaab's Law Deadline Calculator takes the date of a tenant report and calculates every statutory deadline as an exact calendar date, automatically excluding weekends and UK bank holidays. It covers both emergency and significant hazard classifications.